项目管理师

123 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.A. 0.5B. 1.0C. 1.8D. 2.2E. 2.8

题目

123 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

A. 0.5

B. 1.0

C. 1.8

D. 2.2

E. 2.8

参考答案和解析
正确答案:C
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?

A . ¥3,605.00

B . ¥0.57

C . ¥567.00

D . ¥892.86

E . ¥3.61


正确答案:C

第2题:

Using the situation stated in the Special window, what is the total variable costs for producing one widget?

A . ¥1,020

B . ¥1,010

C . ¥1,015

D . ¥20

E . None of the above.


正确答案:E

第3题:

Using the table in the Special window, Which task is completed?

A.dig hole

B.remove debris

C.survey

D.set forms

E.place concrete


正确答案:B
B

第4题:

Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

A . 1.1

B . 0.9

C . 0.956

D . 1.15

E . 0.869


正确答案:A

第5题:

Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

A . 8

B . 8.8

C . 9.1

D . 9.7

E . 10.5


正确答案:B

第6题:

Using the situation stated in the Special window, what is the total price variance for direct material?

A . ¥140.00

B . ¥736.00

C . ¥0.02

D . ¥-350.00

E . ¥5,850.00


正确答案:B

第7题:

Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

A . 0.5

B . 1

C . 1.8

D . 2.2

E . 2.8


正确答案:C

第8题:

Using the situation stated in the Special window, what is the schedule variance for Case #8?

A . 1000

B . 2000

C . -1000

D . -2000

E . 0

.


正确答案:B

第9题:

Using the situation stated in the Special window, the total price variance of direct material is:

A . ¥80,245

B . ¥-4,236

C . ¥-3,479

D . ¥1

E . ¥83,994.00


正确答案:C

第10题:

Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

A . Element P

B . Element Q

C . Element R

D . Element S

E None of the above.


正确答案:D

更多相关问题