123 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A. 0.5
B. 1.0
C. 1.8
D. 2.2
E. 2.8
第1题:
Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?
A . ¥3,605.00
B . ¥0.57
C . ¥567.00
D . ¥892.86
E . ¥3.61
第2题:
Using the situation stated in the Special window, what is the total variable costs for producing one widget?
A . ¥1,020
B . ¥1,010
C . ¥1,015
D . ¥20
E . None of the above.
第3题:
Using the table in the Special window, Which task is completed?
A.dig hole
B.remove debris
C.survey
D.set forms
E.place concrete
第4题:
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A . 1.1
B . 0.9
C . 0.956
D . 1.15
E . 0.869
第5题:
Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A . 8
B . 8.8
C . 9.1
D . 9.7
E . 10.5
第6题:
Using the situation stated in the Special window, what is the total price variance for direct material?
A . ¥140.00
B . ¥736.00
C . ¥0.02
D . ¥-350.00
E . ¥5,850.00
第7题:
Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A . 0.5
B . 1
C . 1.8
D . 2.2
E . 2.8
第8题:
Using the situation stated in the Special window, what is the schedule variance for Case #8?
A . 1000
B . 2000
C . -1000
D . -2000
E . 0
.
第9题:
Using the situation stated in the Special window, the total price variance of direct material is:
A . ¥80,245
B . ¥-4,236
C . ¥-3,479
D . ¥1
E . ¥83,994.00
第10题:
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.