软件水平考试

( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated managementB.Configuration

题目
( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

A.Integrated management
B.Configuration management
C.Scope management
D.Requirements management
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

A.Developing project charter

B.Developing project management plan

C.Analyzing project risks

D.Monitoring and controlling project


正确答案:C

第2题:

__________ is the process of motivating a group of people towards achieving a common goal.

A、Planning

B、Organizing

C、Leading

D、Controlling


参考答案:C

第3题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


正确答案:B

第4题:

After a server has been installed into a rack, an administrator must ensure which of the following?()

A. Warm air flow is permitted through the front bezel

B. The system is labeled so that it can be identified

C. Verify the change control process can be implemented

D. Determine the correct power requirements


参考答案:B

第5题:

Which of the following is not part of the change-management process of IT supervisor?( )

A.change analyses

B.change evaluation

C.change acquisition

D.change executing


正确答案:D

第6题:

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

A.work performance information

B.scope statement

C.change requests

D.process analysis


正确答案:B
解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

第7题:

试题(75)

Which of the following is not part of the change-management process of IT supervisor?(75).

(75)

A.change analyses

B.change evaluation

C.change acquisition

D.change executing


正确答案:D
试题(75)分析
信息工程监理变更控制不包括:
选项A是变更分析,选项B是变更评估,选项C是变更确认,选项D是变更执行。
因此,正确答案是D。
参考答案
(75)D

第8题:

The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out


正确答案:B
执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

第9题:

Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.

A.communicating

B.collecting

C.filing

D.documenting


正确答案:D

第10题:

Requirements management is the process of (1),analyzing,tracing,prioritizing andagreeing on requirements and then controlling changes and communicating to relevantstakeholders.

A.communicating

B.collecting

C.filing

D.documenting


正确答案:D
需求管理过程是(1),分析,跟踪,优先考虑和同意的要求并控制变化和沟通,利益相关者。A、沟通B、收集C、归档D、编制

更多相关问题