The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex. A.Cost AggregationB.Reserve AnalysisC.ParametriC.EstimatingD.Funding Limit Reconciliation

题目
The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex.

A.Cost Aggregation
B.Reserve Analysis
C.ParametriC.Estimating
D.Funding Limit Reconciliation
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A project manager can exchange information with the project team using which media?

A tactile

B audio

C olfactory

D visual

E All of the above.


正确答案:E

第2题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第3题:

A technique that can be used to measure the total income of a project compared to the total moneys expended at any period of time is:

A . return on investment (ROI)

B . net present value (NPV)

C . discounted cash flow (DCF)

D . B and C

E . All of the above.


正确答案:E

第4题:

136 A technique that can be used to measure the total income of a project compared to the total moneys expended at any period of time is:

A. return on investment (ROI)

B. net present value (NPV)

C. discounted cash flow (DCF)

D. B and C

E. All of the above


正确答案:E

第5题:

59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A. Significantly reduce project risks

B. eliminate project risks

C. provide a rational basis for better decision making

D. identify risks, their impact(s), and any appropriate responses

E. None of the above


正确答案:B

第6题:

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A Significantly reduce project risks

B eliminate project risks

C provide a rational basis for better decision making

D identify risks, their impact(s), and any appropriate responses

E None of the above.


正确答案:B

第7题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第8题:

Most project management leadership theories focus on all of the following except:

A . Personal characteristics of the project manager

B . The situation at hand

C . Personal traits of the subordinates

D . Behavioral styles of the project manager

E . Usefulness of authority and power in leadership


正确答案:C

第9题:

155 A project manager can exchange information with the project team using which media?

A. tactile

B. audio

C. olfactory

D. visual

E. All of the above


正确答案:E

第10题:

The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A.costaggregation

B.reserve analysis

C.parametricestimating

D.funding limit reconciliation


参考答案:A

可以注意到该题的关键词为"mathematical model"和"predict total project cost",再划分语句结构"The()technique(主语)involves(谓语)using project characteristics in a mathematical model to predict total project cost",易理解语句含义为"什么技术使用数学模型预测项目的总成本"。观察四个选项,ABD也可能应用数学模型,也可能只是简单的数字规定,但选项C 一定会应用数学模型,所以应该选择parametric estimating。